September 2014
01-Sep-2014
(Mon) Introduction + Technical Visit
14:30-15:30
Introduction to Design Project [Venue: CPD-1.42 ]
15:30-17:00
Technical visit: Robert
Black College
08-Sep-2014
(Mon) Seminar + Design Tutorials [Venue:
CPD-LG.63 ]
14:30-16:00
Seminar: Green
Building Design and Assessment [PDF ]
16:00-17:00
Design Tutorials
15-Sep-2014
(Mon) Seminar + Design Tutorials [Venue:
CPD-LG.36 ]
14:30-16:00
Seminar: Fire Safety
and Statutory
Issues
16:00-17:00
Design Tutorials: Design Brief
22-Sep-2014
(Mon) Seminar + Design
Tutorials
14:30-15:30
Seminar: BSE
Design Guides [PDF ]
15:30-17:00
Design Tutorials
29-Sep-2014
(Mon) Design Tutorials
14:30-17:00
Design Tutorials
October
2014
06-Oct-2014
(Mon) Design Tutorials
14:30-17:00
Design Tutorials
13-Oct-2013
(Mon) [Reading/field trip week] 13_18-Oct-2014
(Submit
Interim Report
on or before 13 Oct 2014)
20-Oct-2014
(Mon) Design
Tutorials (Design drawings and design calculations )
14:30-17:00
Design Tutorials
27-Oct-2014
(Mon) Feedbacks
+ Design
Tutorials (Design specification and design
coordination )
14:30-15:30
Feedbacks on Interim Report
15:30-17:00
Design Tutorials
November
2014
03-Nov-2014
(Mon) Technical visit to Hyatt Regency Hong Kong,
Sha Tin
10-Nov-2014
(Mon) Design Tutorials (Report wr iting
and oral presentation )
14:30-17:00
Design Tutorials
17-Nov-2014
(Mon) Semester 1 Presentation
14:30-17:00
Oral presentations (For each group:
20 minutes presentation + 10 minutes Q&A)
14:30-15:00
Group 1 (Ukulele)
15:00-15:30
Group 2 (Goddess & Partners)
15:30-16:00
Group 3 (GG Dragon)
16:00-16:30
Group 4 (Project Save Our GPA)
16:30-17:00
Group 5 (captain teemo on duty)
24-Nov-2014
(Mon) Deadline
for submitting Semester 1
Report
Length
of the report: maximum 150 nos. A4 pages
(including everything)
Submission:
one hard copy and one PDF electronic copy
December
2014
Revision
and examination period (No activities)
Semester
2 : (Time: Mondays 14:30-17:30, Venue: LG1-09 ,
Composite Building (for the first three weeks)
Venue for week no. 4 to 13 to be confirmed)
January 2015
19-Jan-2015
(Mon) Feedbacks + Introduction
14:30-15:30
Feedbacks on Semester 1 Report
15:30-17:00
Introduction to Technical Analysis
26-Jan-2015
(Mon) Project Meetings
1 5 :30 -17:00
Project Meetings
February
2015
02-Feb-2015
(Mon) Project Meetings
14:30-17:00
Project Meetings
09-Feb-2015
(Mon) Project Meetings
14:30-17:00
Project Meetings
16-Feb-2015
(Mon) Project Meetings
1 5 :30 -17: 3 0
Project Meetings
23-Feb-2015
(Mon) [Chinese New Year holiday] (No class)
March
2015
02-Mar-2015
(Mon) Project Meetings
14:30-17:00
Project Meetings
09 -Mar-2015 (Mon) [Reading/field
trip week] 9_14 -Mar-2015
16-Mar-2015
(Mon) [HKU Foundation Day holiday] (No
class)
23-Mar-2015
(Mon) Project Meetings, Room 7-31, 7/F Haking Wong
Building
14:30-17:00
Project Meetings (findings of technical analysis
and report structure)
A
Report Checklist (Lincoln
University) [PDF ]
Minor
thesis & research report structure (RMIT) [PDF ]
30-Mar-2015
(Mon) Project Meetings , Room 7-37,
7/F Haking Wong Building
14:30-17:00
Project Meetings (report writing and oral
presentation)
April
2015
06-Apr-2015
(Mon) [Easter Monday holiday] (No class)
13- and
15-Apr-2015 (Mon & Wed) Semester
2 Presentation
13-Apr-2015
(Mon) 14:30-17:30 Oral presentations [HW7-37, 7/F
Haking Wong Building]
15-Apr-2015
(Wed) 09:30-12:30 Oral presentations [HW7-37, 7/F
Haking Wong Building]
20-Apr-2015
(Mon) Deadline